Tag Archives: library

Loan for Central Library building – request to be considered by City Council

The reason for the quick RPL Board meeting on June 11th (see below) has become apparent !

On June 19 and June 26 City Council is set to approve a $119 Million loan for Central Library as part of long-term debt financing for the City.

“For the Central Library Renewal Project, the City will consider incurring debt in the maximum principal sum of $119 million. As part of this the City will consider the possibility of applying to the Saskatchewan Municipal Board for a debt limit increase from the current debt limit of $660 million to accommodate proceeding with this project. The goal of the Central Library Renewal Project is to provide a renewed Central Library to respond to community priorities, enhance Regina Public Library programs and services, improve quality of life for all, and support economic growth.”

City ad about vote and how to put in submissions, here City loan request for Central – ad June 8, 2024 and link.
https://www.regina.ca/export/sites/Regina.ca/city-government/city-page/.galleries/pdfs/June-8-2024-CityPage.pdf

To be “… considered by the City’s Executive Committee on June 19 at 9:00 am and City Council on June 26, 2024 at 1:00 p.m and may also be considered at subsequent meetings. Citizens who want to address the Executive Committee on June 19, 2024 may attend via teleconference or in person. To attend, you must register by completing the online form on Regina.ca/register no later than noon on June 17, 2024. … Citizens who want to address City Council on June 26, 2024 may attend the meetings via teleconference or in person. To attend Council, you must register by completing the online form on Regina.ca/register to request to address City Council on these matters. The deadline to register is no later than noon on June 24, 2024.  A written brief is required to present at a Council meeting.  Find more information about presenting to Council and Committees on Regina.ca. If attending by teleconference you must also provide the telephone number you will be using to call into the meeting with, when registering. You will receive meeting details and instructions after you have confirmed your attendance for the meeting.”

A June 2023 request to increase City debt by $330M was rejected by the Saskatchewan Municipal Board, who asked the City to reduce their request to $210M, for a total debt limit of $660M 
https://leaderpost.com/news/local-news/city-hall/city-asked-to-lower-debt-limit-request-to-660m-budget-preview

New services & locations May 11 & 15

RPL new locations AND services for large branches

Very Important – Please Register & Attend: RPL sessions on new locations & services, and enhanced services for large branches. This could include Central, as well as other branches. And services to areas without a nearby library branch. https://www.reginalibrary.ca/renewal

George Bothwell Branch, Sat. May 11 12:30 p.m. Register here: https://www.reginalibrary.ca/attend/programs/10753823

Sunrise Branch, Wed. May 15 7:00 p.m., Register here: https://www.reginalibrary.ca/attend/programs/10753835

PREVIOUSLY, RPL HAD DONE AN ONLINE SURVEY ON THIS TOPIC, that was available on their website.

MORE DETAIL IN ORIGINAL ANNOUNCEMENT OF EVENTS FROM RPL “RPL is hosting a public engagement session focused on potential new RPL service locations and the scope of associated services. At this public engagement session, members of our project team will present the findings and data collected in this project so far and facilitate discussions to gather community feedback on possible locations for new RPL service points and the type of services offered at those locations, as well as what enhanced services at our large branches might include in the future.“ More detail here: https://www.reginalibrary.ca/renewal

Citizens denied voice at RPL mtg on Central Library

RPL Board denied the opportunity for FRPL and other citizens to make presentations to the RPL Board at a critical meeting about the future of Central Library.

The RPL’s draft agenda, posted on Friday July 14, for which citizens had only until Tuesday July 18 at noon to write a presentation and request to make a presentation, included:

8. Discussion and decision items

(a) Board Committees

iv) Strategic Planning Committee

(1)  Project Charter

(2)  Project Governance Terms of Reference

(3)  Colliers Statement of Work for Central Library Renewal Project

(4)  Colliers Statement of Work for Central Library Temporary Relocation Project

(5)  Branch renewal update

FRPL and other citizens sent in letters requesting to make presentations at the RPL Board meeting on July 25, 2023. In its letter FRPL restated our position that it would be better to expand on the new building, rather than tear it down and rebuild. We went on to ask questions about the criteria for future development and public participation processes. FRPL presentation FRPL to RPL Board July 18, 2023 – fina

On July 21 RPL sent the following email:

.. The topics represented in your submission do not align with topics on the agenda. The Library Board decision made in September 2022 is not under review and the Board’s work to move forward supports its decision to build a new Central Library, with a preference for the current location. The Library’s engagement of Colliers Project Leaders as its owner’s representative was undertaken over three years ago and is not under review. The Library Board does not have purview over how City Council allocates project funding. The many other topics you have included are not in question at this meeting.

As outlined in the Submissions and Delegations Policy, your submission will be included in the Board’s package for their information and later posted to the RPL website. …”

Similar emails were sent in response to Jeannie Mah RPL Board. July 2023 and Florence Stratton LIBRARY BOARD, CENTRAL LIBRARY, JULY 25 2023

The RPL Board continues its efforts to restrict public discussion of its decisions or future plans. Unlike City Council, the RPL Board does not release any details in advance about its agenda items. Reports given at the “public meetings” are not published along with the minutes. The minutes only appear publicly over 2 months after the meetings, after they are approved by the RPL Board at its subsequent meeting, then eventually posted on their website.

NEVERTHELESS, CITIZENS ARE URGED TO ATTEND THE NEXT RPL BOARD MEETING ON JLUY 25 AT 4:30 PM. Check details on the day of the meeting to confirm. https://www.reginalibrary.ca/about/leadership/board-meetings-2023

  • In person, at the RPL Boardroom on the second floor of Central Library..
  • Via Microsoft Teams – you must email the RPL in advance to be included on the list.
  • Or by teleconference: check the RPL agenda for the conference call-in number and password.

Central plans at RPL Board July 25 – make your views known

RPL is moving ahead with plans to demolish Central and rebuild. Plans will be discussed at their July 25 Board meeting.  Draft agenda 0-Draft Agenda – posting 20230714 Go to the RPL website for the final agenda. https://www.reginalibrary.ca/about/leadership/board-meetings-2023

Requests for presentation to the July 25 Board meeting must be in by Tues. July 18 at 12 noon. https://reginalibrary.ca/about/leadership/presenting-to-the-board

Recent developments:

Please express your views by:

  • Sending in a letter, and a request for submission, to RPL Board by Tues. July 18 at 12 noon
  • Sending letters or email or phoning the RPL Board and your City Councillors
  • Attending the July 25 RPL Board meeting. to hear what the plans are for Central. This can be done in person, connecting by hone, or connecting through Microsoft Teams. You need to register in advance for connecting to Microsoft Teams, and also download the software. In-person: Central Library Boardroom
    Online: email librarydirectorsoffice@reginalibrary.ca for Microsoft Teams link
    Dial-in: 1 (647) 749-9317, meeting passcode 183 336 408#

Demolition of Central would have to be approved by

  • Regina City Council
  • Saskatchewan Heritage Properties Review Board (because Central is part of the Victoria Park Heritage Conservation District)
  • What are the prospective timelines and/or deadlines?
  • How does the RPL Board justify the destruction of a heritage building?

Concerns and possible questions from FRPL

  • RPL Board interpretation and reporting to City Council of cost estimates inaccurate for upgrading the current building, resulting in claims that it is not possible to rehabilitate the building
  • Maintaining the current building
  • Preserving its heritage
  • Specifics about including preservation of heritage in the requests for proposals to architects
  • Costs of relocation (budget for the move, budget for the demolition and budget for new construction). Will there be financials in the statement of work documents?
  • What are the plans and timeline for securing the money for any changes?
  • Changes to current situation should not be approved until clear plans are in place.  We all know of the projects recently that have collapsed after the initial fanfare, think Centre Pointe and Namerind.  What contingencies are in place for unforeseen delays or overrun budgets?
  • When will project management reports, such as those being discussed at the July 25, 2023 meeting, be available to the public? (project charter and the two statements of work)
  • Colliers has been hired to project manage both the temporary relocation project and the rebuild.  What expertise and experience has Colliers got that give the public confidence about their competence, especially in new construction?
  • Does the Library Board do this directly or through a subcommittee of the Board?
  • How much is the City of Regina involved, such as a city project manager? What is the “chain of command” and where does the final accountability reside? Will there be opportunities for the public to review and comment on decisions throughout the process?
  • What are the plans for public consultation?  Will there be regular opportunities for engagement and the ability to question plans?  Will a public design charette be used to engage and explore how this rebuild will fit with the public’s expertise and knowledge of building design and desired uses of libraries? How will the disability community and individuals or those with specialized needs be engaged throughout the process?
  • Will this rebuild be a net-zero carbon building?  What opportunities will there be to capture or reduce the carbon footprint of this rebuild?  Will this be put into the request for proposals?

Catalyst Conversation Nov 24 will include Library

THURSDAY NOVEMBER 24, 7:30 pm: CATHEDRAL CATALYST CONVERSATION, CATHEDRAL NEIGHBOURHOOD CENTRE, 2900 13TH AVE

A chance to learn about, provide feedback on the city’s Catalyst Projects. Ward 3 City Councillor Andrew Stevens will be there to answer questions.

Two opinions about Saskatoon’s proposed new library

FRPL is VERY supportive of libraries. And so we support public discussion of different views about libraries. These are two opinions on Saskatoon’s new proposed downtown library.

Yann Martel: Replacing Saskatoon’s decrepit downtown library no luxury:

As the cost of living goes up and up and up — groceries, houses, restaurants and so on — libraries are still free. Yann Martel Oct 19, 2022  •  October 20, 2022  https://thestarphoenix.com/opinion/columnists/yann-martel-replacing-saskatoons-decrepit-downtown-library-no-luxury

Cary Tarasoff: Martel glazes over new Saskatoon library’s real issues:

A former Saskatoon mayoral candidate thinks the proposed new downtown Saskatoon library represents an unnecessary expense. Cary Tarasoff Oct 25, 2022 https://thestarphoenix.com/opinion/columnists/cary-tarasoff-martel-glazes-over-new-saskatoon-librarys-real-issues

Saskatoon Public Library releases final design for new central branch:

Library CEO says project remains on time and on budget. Bryn Levy Oct 11, 2022 https://thestarphoenix.com/news/local-news/saskatoon-public-library-releases-final-design-for-new-central-branch

FRPL submissions to Catalyst Committee

The text of our presentation FRPL to Catalyst Committee, Oct 20, 2022 – Final

A display about libraries that have made additions to their buildings instead of tearing them down. FRPL Library Additions Display for Catalyst Ctte Oct 20, 2022

Tours of Central: Oct 25 to 29

Regina Public Library is hosting tours from Oct 25 to 29, 2022 “to share information about the history of the building and some of the issues we are facing. Join us for a guided tour to hear about key concerns and remediation RPL has been undertaking to keep it safe. There will be opportunity to ask questions along the way. This tour provides a chance to learn more about the Central Library Renewal (CLR) project, one of the infrastructure projects being reviewed by the City of Regina’s Catalyst Committee. Tours begin in the lobby and will last approximately one hour. Tues, Oct 25 2:00pm – 3:00pm, Wed, Oct 26 2:00pm – 3:00pm, Wed, Oct 26 6:00pm – 7:00pm, Thurs, Oct 27 6:00pm – 7:00pm, Sat, Oct 29 10:00am – 11:00am For more information, and to register for a tour: https://central.reginalibrary.ca/” You must preregister – have your library card handy or be prepared to sign up for one.

Note that these tours are supposed to talk about the heritage aspects of the building, but their main focus will be on the problems with the building, to justify the RPL Board’s decision to tear it down. So be prepared for this line of thought, and your questions about the building.

Deadline Oct 31st: letters to Catalyst Committee

Deadline Oct 31st:  Send presentations that were given to the RPL Board, presentations given at Catalyst Committee and other thoughts to Catalyst Committee.  

It has been suggested to us that it would be good to have your presentations and letters sent to the Catalyst Committee by the end of October.

Send to:  Attention Co-chairs Tim Reid + Bob Hawkins at catalyst@regina.ca and

Tim Reid at tim.reid@real1884.ca and dakota.schmidt@real1884.ca 

Bob Hawkins at  bhawkins@regina.ca 


Cc: Regina City Council Clerks at clerks@regina.ca  – to forward to Mayor and all Council.

Public can listen, present at Catalyst Ctte

Reminder of this week’s meetings of the Catalyst Committee. See important articles and letters to the editor https://friendsofrpl.ca/central-branch-2021/media-coverage-central-library-2022/

Information on the Catalyst Committee https://beheard.regina.ca/catalyst-committee Regina Residents Invited to Provide Input on Once-in-a-Generation Catalyst Committee Projects, October 7, 2022 https://www.regina.ca/news/Regina-Residents-Invited-to-Provide-Input-on-Once-in-a-Generation-Catalyst-Committee-Projects/

Their report to Council in January 2023 will have a major influence on projects that will receive City Council support in the future.

Sessions Oct. 17 to 20, 11 am to 1 pm and 5 pm to 7 pm
AGT Lounge, enter by Northwest door at Mosaic Stadium. Use Elevator 2 to the 3rd floor.
Parking in nearby lots, bus #12

Project proponents will make first presentation of about 30 minutes.
Members of the public can make presentations, 5 to 10 minutes is suggested, but there is no set time limit. You don’t have to submit your presentation in advance. You can bring PowerPoint presentations on a USB stick.

Monday: Multi-Purpose Event Centre
Tuesday: Regina Aquatics Centre
Wednesday: Multi-Purpose Outdoor Baseball Event Centre & Synthetic Outdoor Field Project (joint presentation)
Thursday: Modernization of the Central Library

People can sent in emails / letters to the Catalyst Committee.
 For full consideration, get them in by the end of October. Email questions and submissions to clerks@regina.ca with the subject line  “Catalyst Committee”.

The BEHEARD survey will be posted on the City of Regina website (www.beheard.regina.ca/catalyst-committee) starting on October 17th.  

There is no arrangement for broadcasting the event on the internet, so no ability to make a presentation remotely or to hear what is being said.

People can create display storyboards, to be at the AGT location by Friday Oct 14 or befor 11 am on the 17th

There is no downtown location for a discussion of the downtown.